What Are CFA Piles? A Guide to CFA Piling in Construction
If you work across commercial, residential or infrastructure projects, there is a good chance you have come across CFA piling.
What are CFA piles, and how do they differ from other bored piling methods? Let’s break down the details.
Key Takeaways
CFA piles are installed using a continuous flight auger with no open borehole.
They work well in softer soils and areas with high groundwater.
CFA piling is fast and produces relatively low vibration.
Hard rock and buried obstructions can limit where CFA piling is suitable.
CFA piles usually need cropping before pile caps or ground beams are built.

What Are CFA Piles and How Are They Used in Construction?
CFA stands for Continuous Flight Auger. The method uses a hollow-stem auger to drill to the required depth. Concrete is then pumped through the centre of the auger as it is withdrawn. Reinforcement is inserted into the fresh concrete afterwards. Because the auger remains in the ground until concreting begins, there is no open borehole during the process.
For construction teams, this makes CFA piling a practical option on sites with softer soils, groundwater or tight programmes.
CFA Piles Installation Process
To understand what CFA piles are, it helps to look at the installation process:
Positioning the rig: The piling rig is set over the pile location.
Drilling to depth: A continuous flight auger is drilled into the ground, carrying spoil up to the surface as it advances.
Pumping the concrete: Once the design depth is reached, concrete is pumped through the hollow centre of the auger.
Withdrawing the auger: The auger is gradually lifted while concrete fills the space.
Inserting the reinforcement: The reinforcement cage is placed into the wet concrete once the auger is clear.
Because the bore is supported throughout drilling and concreting, there is less risk of collapse in loose or unstable ground.
Where Are CFA Piles Used?
CFA Piles are common across a wide range of construction projects. They are often used for:
Multi-storey residential developments
Commercial buildings
Industrial sites
Civil and infrastructure projects
Sites close to existing structures
CFA piling is particularly useful where lower vibration is preferred. It also suits sites with high groundwater, ensuring an open bore is supported before concrete is poured. The method also helps crews complete more piles in less time and keep the job moving.
CFA Piles vs Bored Piles
When comparing CFA piles vs bored piles, the main difference is how the bore is formed and concreted. Other key differences include:
Factor | CFA Piles | Bored Piles |
Installation | Concrete is pumped through the auger as it is withdrawn, so there is no open borehole. | The hole is drilled first, then reinforcement and concrete are placed. |
Ground conditions | Well suited to softer soils, loose ground and high groundwater. | Better suited to harder ground and rock conditions. |
Speed | Often faster on larger projects with high pile volumes. | Can be slower depending on drilling and bore support requirements. |
Bore support | The auger supports the bore until concrete is placed. | Temporary casing or support fluid may be required. |
The CFA piles vs bored piles difference often comes down to the ground conditions, project size and site requirements.
Our take: CFA piling can be faster on larger projects and tends to work well in soft soils and high groundwater. Bored piles can be a better fit where hard rock is present or where the project does not justify mobilising a CFA rig.
What Are the Limitations of CFA Piling?
CFA piling works well in the right conditions, but it is not suitable everywhere. Its limitations include:
Hard rock: CFA augers can struggle to penetrate competent rock, which may require a different piling method.
Buried obstructions: Old footings, masonry, large boulders and other unexpected materials can stop or slow drilling.
Contaminated ground: Needs careful planning because spoil is brought to the surface during drilling. That material may need specialist handling and disposal.
To confirm whether CFA piling is appropriate for your site, we highly recommend conducting ground investigations before piling starts.
What Happens After CFA Piles Are Installed?
Part of understanding what CFA piles are is knowing what happens after installation. CFA piles are usually cast above the final cut-off level, so excess concrete needs to be removed before pile caps or ground beams are built.
This is known as pile breaking.
A hydraulic CFA pile cropper removes the excess concrete while keeping the required reinforcement intact. Depending on the design, rebar may be left exposed, or the pile may be cropped flatter.

Mr Cropper also offers CFA cropper hires. For larger projects, our guide to choosing pile trimmers covers what to consider before work begins.
For a more accurate quote and process walkthrough, connect with our team today.
CFA Piles FAQs
What do CFA piles mean in construction?
The CFA piles stand for Continuous Flight Auger piles. They are cast-in-situ concrete piles installed using a hollow continuous auger, with concrete pumped through the auger as it is withdrawn.
Why are CFA piles used?
CFA piles’ meaning and function are closely tied to the installation method. Because the auger stays in place until concreting starts, CFA piling works well in softer soils, loose ground and areas with higher groundwater.
Do CFA piles need cropping?
Yes, in most cases. CFA piles are usually installed above the final cut-off level, so the excess concrete needs to be removed before the next foundation elements are constructed.
Can CFA piles go through hard rock?
CFA piling is not generally suited to competent hard rock. Where hard rock or major obstructions are present, another piling or drilling method may be more appropriate.